The Process & Timelines

The duration of the solar installation process can vary depending on several factors, including location, permitting requirements, and any additional work needed.

<aside> 💡

You will have access to your own Customer Portal to conveniently track their project status and access important documentation.

</aside>

You will receive timely updates from Better Earth via texts and emails, informing you about project progress. Updates will include key milestones like documentation submission, scheduling installations, inspections, and activation calls. Effective communication is vital for a smooth and transparent solar installation experience.

In addition to receiving text and email updates, you can also contact us. Our dedicated support team is always ready to assist you with any questions or concerns you may have. We take pride in offering prompt and helpful assistance to ensure a smooth customer experience.

Here's an overview of the typical timeline for a solar installation with Better Earth:


Stage-by-Stage

Overall the entire process can take anywhere from 60 - 120 Days from start to finish, depending on where you live and what equipment is getting installed.

  1. Sale > Site Survey: 1-3 Days

  2. Site Survey > Design Complete: 2-4 Days

  3. Design Complete > Permit Submission: < 7 Days